Server and UI Deployment - 22nd May 2024

Scheduled Maintenance Report for Amadeus

Completed

The scheduled maintenance has been completed.
Posted May 23, 2024 - 00:37 AEST

Update

Optimizer started and Verification is currently underway for the deployment items.
Posted May 23, 2024 - 00:01 AEST

Update

Stopped optimizer and Proceeding for server & GUI deployment
Posted May 22, 2024 - 23:04 AEST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 22, 2024 - 23:00 AEST

Scheduled

A new patch will be deployed tonight at 23:00 AEST. This patch will include following fixes/new features:

GUI features:
- Feature to activate or disable the ability to use CTRL-Shift-D with a switch to reactivated if needed.

Recovery Optimizer features:
- ORO - Station break at the beginning of the RW cannot be solved when there is a ground return
- ORO - Optimiser failed to return a solution due to an error in creating merged requests

Bug fixes:
- [PTR] CloseAllOutdatedEvents job not running in PRD
- ORO - Cannot open offline instances

Spikes/technical improvements:
- [STORY] Auto closure for events
- [Story] Use SecretsManager for all secrets - Codebase - remove hardcoded credentials
- [TASK] Use SecretsManager for all secrets - CI/CD - AWS OIDC non-prod part 2

Please note that:
* Slot optimization on all TMIs will be stopped and restarted after the patch deployment.
* All frozen slots data will be maintained as it was before patch deployment.

Once the patch is deployed, users have to update their UI,
* either by checking from Help -> Check for Updates and accepting the updates and finally restarting the UI.
* or, by restarting COMPASS and then accepting the update notification.
Posted May 22, 2024 - 17:11 AEST
This scheduled maintenance affected: ASR API, AsA Metron Interface, and OGS Interface.